| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 02 Sep 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending...Sec. Clarifier 1 launder slab sidewall shuttering work in progress....Sec.Clarifier 2 walkway shuttering and reinforcement work in progress....MCC Room foundation backfilling work in progress.... | Kollam Project HD | |
| 01 Sep 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending...Sec. Clarifier 1 launder slab sidewall shuttering work in progress....Sec.Clarifier 2 walkway shuttering and reinforcement work in progress.... | Kollam Project HD | |
| 31 Aug 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending | Kollam Project HD | |
| 30 Aug 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending | Kollam Project HD | |
| 28 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site,Transformer room foundation footing shuttering work in progress...Sec. Clarifier 1 launder slab sidewall reinforcement and shuttering work in progress....MBBR 3&4 connecting channel reinforcement work in progress.... | Kollam Project HD | |
| 25 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site,Transformer room foundation footing shuttering work in progress...Sec. Clarifier 1 launder slab sidewall reinforcement and shuttering work in progress....MBBR 3&4 connecting channel reinforcement work in progress.... | Kollam Project HD | |
| 24 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site,Transformer room foundation footing shuttering work in progress...Sec. Clarifier 1 launder slab sidewall reinforcement and shuttering work in progress....MBBR 3&4 connecting channel reinforcement work in progress....Mechanical erection Header fixing work in progress... | Kollam Project HD | |
| 23 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site,MBBR 3&4 connecting channel piller reinforcement work in progress...CCT final lift sidewall shuttering work in progress....Sec. Clarifier 2 center shaft fourth lift shuttering work in progress...Sec. Clarifier 2 center shaft fourth lift reinforcement work in progress...Sludge drying bed flooring work started...Transformer factory testing completed successfully. | Kollam Project HD | |
| 22 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site,CCT final lift side wall shuttering work in progress...MBBR 1outlet chamber finel lift reinforcement and shuttering work in progress... Mechanical erection in progress... MBBR 3 and 4 piller footing reinforcement work in progress centrifuge building staircase foundation mat reinforcement work in progress... | Kollam Project HD | |
| 21 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site ,sec..clarifier 2 center shaft form work In progress...CCT walk way reinforcement work in progress... MBBR 1 and 2 connecting channel wall shuttering work In progress... | Kollam Project HD |