Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Oct 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending...MBBR 3-4 Connecting channel shuttering work in progress....Sec. Clarifier 2 & CCT connecting channel shuttering work in progress...Pile cap reinforcement work for admin building in progress.... Kollam Project HD
01 Oct 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending.MBBR 3&4 connecting channel shuttering work in progress...Sec. Clarifier 2 & CCT connecting channel shuttering work in progress....Sec. Clarifier 1 center shaft final lift shuttering work in progress.... Kollam Project HD
30 Sep 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending.Sec. Clarifier 2 & CCT connecting channel shuttering work in progress...MBBR 3&4 connecting channel shuttering work in progress...Air blower building wall plastering work in progress.... Kollam Project HD
29 Sep 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending.Sec. Clarifier 2 & CCT connecting channel reinforcement and shuttering work in progress...Sec. Clarifier 1 center shaft final lift shuttering work in progress..MBBR 3&4 connecting channel shuttering work in progress... Kollam Project HD
28 Sep 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..MBBR 4 Recirculation pump erection work in progress....Sec. Clarifier 2 & CCT connecting channel reinforcement work in progress....MBBR 3&4 connecting channel shuttering work in progress.... Kollam Project HD
27 Sep 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..Sec. Clarifier 1 center shaft Final lift reinforcement and shuttering work in progress...Sec. Clarifier 2 launder weir wall shuttering work in progress...MBBR 2 Re-circulation pump erection work in progress....Sec. Clarifier 2 & CCT connecting channel reinforcement work in progress... Kollam Project HD
26 Sep 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..Sec. Clarifier 2 launder weir wall shuttering work in progress....Sludge thickener mechanism erection work in progress...Sec. Clarifier 1 staging work in progress for centre shaft and bridge erection.... Kollam Project HD
25 Sep 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..Sec. Clarifier 1 & CCT connecting channel reinforcement work in progress...Air blower foundation grouting work in progress....Centrate pump erection work in progress..Sludge thickener EM positioning and erection in progress...Sludge thickener mechanism erection work in progress...Sec. Clarifier 1 staging work in progress for centre shaft and bridge erection.... Kollam Project HD
24 Sep 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..Sec. Clarifier 1 & CCT connecting channel reinforcement work in progress...Equalization tank staircase curing work in progress...MBBR 3&4 connecting channel curing work in progress...Centrate sump coal tar epoxy coating work in progress....Equalization tank raw sewage transfer pump erection work in progress... Kollam Project HD
23 Sep 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..Centrifuge feed pump foundation RCC work completed...Equalization tank staircase RCC completed...MBBR 3&4 connecting channel slab RCC completed... Kollam Project HD