Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Oct 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending ..Equilization tank and Inlet chamber hand railing work in progress....Admin building plinth beam reinforcement work in progress...Grit chamber hand railing progress.. Kollam Project HD
21 Oct 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending ...Earth strip laying work in progress...MCC Room lintel form work in progress...Earthwork for aerator completed...Inlet chamber Hand Railing work in progress.... Kollam Project HD
20 Oct 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending ...Earth strip layi...ng work in progress...MCC Room lintel form work in progress...Earthwork for aerator completed...Inlet chamber Hand Railing work in progress.... Kollam Project HD
19 Oct 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending ..Admin building plinth beam reinforcement work in progress...Transformer room column starter rcc work completed...Equalization tank Hand Railing work in progress... Kollam Project HD
18 Oct 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending Transformer room column reinforcement work in progress...Admin building column reinforcement work in progress....Equalization tank Hand Railing work in progress... Kollam Project HD
17 Oct 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending Transformer room column reinforcement work in progress...Admin building column reinforcement work in progress....Equalization tank Hand Railing work in progress... Kollam Project HD
16 Oct 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending.Admin building column reinforcement work in progress...Aerator footing excavation work in progress...Equalization tank Hand Railing work in progress Kollam Project HD
15 Oct 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending.Transformer room plinth beam rcc work completed..Equalization tank Hand Railing work in progress... Kollam Project HD
14 Oct 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending.Sludge Thickener mechanism erection work in progress...Sec.Clarifier 1 centre shaft final lift rcc work in progress...Transformer room plinth beam rcc work in progress... Kollam Project HD
13 Oct 2023 Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..Admin building column reinforcement work in progress..Equalization tank Hand Railing work in progress...Transformer room plinth beam shuttering work in progress...Aerator footing excavation in progress... Kollam Project HD