| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 22 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending ..Equilization tank and Inlet chamber hand railing work in progress....Admin building plinth beam reinforcement work in progress...Grit chamber hand railing progress.. | Kollam Project HD | |
| 21 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending ...Earth strip laying work in progress...MCC Room lintel form work in progress...Earthwork for aerator completed...Inlet chamber Hand Railing work in progress.... | Kollam Project HD | |
| 20 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending ...Earth strip layi...ng work in progress...MCC Room lintel form work in progress...Earthwork for aerator completed...Inlet chamber Hand Railing work in progress.... | Kollam Project HD | |
| 19 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending ..Admin building plinth beam reinforcement work in progress...Transformer room column starter rcc work completed...Equalization tank Hand Railing work in progress... | Kollam Project HD | |
| 18 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending Transformer room column reinforcement work in progress...Admin building column reinforcement work in progress....Equalization tank Hand Railing work in progress... | Kollam Project HD | |
| 17 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending Transformer room column reinforcement work in progress...Admin building column reinforcement work in progress....Equalization tank Hand Railing work in progress... | Kollam Project HD | |
| 16 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending.Admin building column reinforcement work in progress...Aerator footing excavation work in progress...Equalization tank Hand Railing work in progress | Kollam Project HD | |
| 15 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending.Transformer room plinth beam rcc work completed..Equalization tank Hand Railing work in progress... | Kollam Project HD | |
| 14 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending.Sludge Thickener mechanism erection work in progress...Sec.Clarifier 1 centre shaft final lift rcc work in progress...Transformer room plinth beam rcc work in progress... | Kollam Project HD | |
| 13 Oct 2023 | Civil works - 6% pending excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 95% pending..Admin building column reinforcement work in progress..Equalization tank Hand Railing work in progress...Transformer room plinth beam shuttering work in progress...Aerator footing excavation in progress... | Kollam Project HD |