| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 20 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site ,CCT final lift sidewall shuttering work in progress...sec.clarifier 1 centre shaft form work in progress...clarifier 2 walkway shuttering work in progress...MBBR 1 and 2 connecting channel wall shuttering work in progress... | Kollam Project HD | |
| 19 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site ,CCT final lift sidewall shuttering work in progress...sec.clarifier 1 centre shaft form work in progress...clarifier 2 walkway shuttering work in progress | Kollam Project HD | |
| 18 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site ,CCT final lift sidewall shuttering work in progress...Transformer room footing reinforcement work in progress....Borewell yield test started...Air blower building block work in progress.... | Kollam Project HD | |
| 17 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , MBBR 1&2 connecting channel Rcc work completed...Septage transfer pump erection work in progress....CT final lift sidewall shuttering work in progress...Air blower building block work in progress...Sludge Thickner mechanical erection... | Kollam Project HD | |
| 16 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , CCT final lift sidewall shuttering work in progress...Clarifier 2 sidewall curing work in progress....Centrifuge building parapet wall block work in progress....Transformer room footing reinforcement work in progress..MBBR 3 outlet chamber ready for concrete...MBBR 1 and 2 connecting channel rcc work in progress.. | Kollam Project HD | |
| 15 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Equalization tank mechanical erection work started...Transformer room footing reinforcement work in progress...Centrifuge building first floor block work in progress...Clarifier 1 walkway curing work in progress.... | Kollam Project HD | |
| 14 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Equalization tank mechanical erection work started...Transformer room footing reinforcement work in progress...Centrifuge building first floor block work in progress...Clarifier 1 walkway curing work in progress.... | Kollam Project HD | |
| 13 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet.Clarifier 1 walkway curing work in progress.Clarifier 2 center shaft third lift reinforcement work in progress..Centrifuge building 1 center shaft fourth lift reinforcement work in progress...MBBR 1-2 Connecting channel slab ready for concrete...Clarifier 2 sidewall final lift RCC in progress.... | Kollam Project HD | |
| 12 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet.Clarifier 1 walkway curing work in progress...Mbbr1 and 2 connecting channel shuttering work in progress...Centrifuge building first floor block work started...Mechanical pre erection work in progress | Kollam Project HD | |
| 11 Aug 2023 | Civil works - 17 components completed out of 35 , Electro - Mechanical items - 23 out 32 supplied at site , Errection works not started yet.Sec. Clarifier 1 walkway RCC work in progress...Sec. Clarifier 2 centre shaft second lift RCC in progress...Sec. Clarifier 1 walkway RCC work completed...Septage tank pre cast manhole cover slab RCC in progress... | Kollam Project HD |