| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 Nov 2023 | Civil works - RCC works - 26 out of 35 components -100 percent completed... 22 out of 32 items electromechanical supplied ..Filltration unit side wall reinforcement work in progress...Mbbr 3 circulation pump pipe grinding works in progress...Painting progress... | Kollam Project HD | |
| 10 Nov 2023 | Civil works - RCC works - 26 out of 35 components -100 percent completed... 22 out of 32 items electromechanical supplied . Aerator footing rcc completed..Sec. Clarifier 1&2 to CCT connecting channel slab rcc work completed | Kollam Project HD | |
| 09 Nov 2023 | Civil works - RCC works - 26 out of 35 components -100 percent completed... 22 out of 32 items electromechanical supplied . Aerator footing works, Painting works in progress | Kollam Project HD | |
| 08 Nov 2023 | Civil works - RCC works - 26 out of 35 components -100 percent completed... 22 out of 32 items electromechanical supplied . Aerator footing works, Painting works in progress | Kollam Project HD | |
| 07 Nov 2023 | Hon. Mayor kollam conducted review meeting at Mayor Chamber and directed the contractor to finish all works by 15 th Dec.2023 and DDC , Kollam visited the site at 3.0 pm and directed the contractor to finish all works by Dec.2023 | Kollam Project HD | |
| 07 Nov 2023 | Civil works - 4% pending ( 22 m3 RCC work ) excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 65% pending...Cable trench cable laying work in progress.... Transformer room second lift reinforcement work in progress...Mechanical erection progress.... | Kollam Project HD | |
| 06 Nov 2023 | Civil works - 4% pending ( 22 m3 RCC work ) excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 65% pending.... Transformer room second lift reinforcement work in progress...Mcc room lintel rcc work completed...Mechanical erection work in progress... | Kollam Project HD | |
| 05 Nov 2023 | Civil works - 4% pending ( 22 m3 RCC work ) excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 65% pending....Admin building column starter work in progress...Mechanical erection work in progress...Admin building plinth beam curing work in progress.... | Kollam Project HD | |
| 04 Nov 2023 | Civil works - 4% pending ( 22 m3 RCC work ) excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 65% pending....Admin building plinth beam concrete work in progress...Painting progress... Mechanical erection progress.... Boundary wall pile cap & plinth beam form work in progress... | Kollam Project HD | |
| 03 Nov 2023 | Civil works - 4% pending ( 22 m3 RCC work ) excluding admin building , Electro mechanical works - 35% supply pending , Erection works - 65% pending...Boundary wall pile cap & plinth beam form work in progress....Mechanical erection work in progress...Admin building plinth beam form work in progress...Painting progress.... | Kollam Project HD |