Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Nov 2023 Civil works - RCC works - 26 out of 35 components -100 percent completed... 22 out of 32 items electromechanical supplied ....MBBR 3&4 connecting channel sidewall rcc work completed.. Painting and Mechanical erection progress... Kollam Project HD
22 Nov 2023 Civil works - RCC works - 26 out of 35 components -100 percent completed... 22 out of 32 items electromechanical supplied ....Aerator Room plinth beam rcc work completed...Filter unit foundation sidewall rcc work completed...MBBR 3&4 connecting channel sidewall rcc work in progress.. Kollam Project HD
21 Nov 2023 Civil works - RCC works - 26 out of 35 components -100 percent completed... 22 out of 32 items electromechanical supplied ....Boundary wall pile cap and plinth beam form work in progress ...Aerator Room plinth beam form work in progress Mechanical erection and painting progress... Kollam Project HD
20 Nov 2023 Civil works - RCC works - 26 out of 35 components -100 percent completed... 22 out of 32 items electromechanical supplied ....Aerator Room plinth beam form work in progress Mechanical erection and painting progress... Kollam Project HD
19 Nov 2023 Civil works - RCC works - 26 out of 35 components -100 percent completed... 22 out of 32 items electromechanical supplied ....Aerator Room plinth beam reinforcement work in progress...Mechanical erection progress...painting progress.... Kollam Project HD
18 Nov 2023 Civil works - RCC works - 26 out of 35 components -100 percent completed... 22 out of 32 items electromechanical supplied ..Aerator Room plinth beam reinforcement work in progress.... Mechanical work and painting progress...Sec. Clarifier 2 & CCT connecting channel sidewall rcc work completed Kollam Project HD
17 Nov 2023 Civil works - RCC works - 26 out of 35 components -100 percent completed... 22 out of 32 items electromechanical supplied ..Aerator Room plinth beam reinforcement work in progress...Sec. Clarifier 1 & CCT connecting channel sidewall form work in progress... Mechanical work and painting progress... Kollam Project HD
15 Nov 2023 Civil works - RCC works - 26 out of 35 components -100 percent completed... 22 out of 32 items electromechanical supplied ..Transformer room column second lift concrete work completed...MCC room cable tray opening lintel concrete work in progress...Painting and Mechanical erection progress... Kollam Project HD
14 Nov 2023 Civil works - RCC works - 26 out of 35 components -100 percent completed... 22 out of 32 items electromechanical supplied ..Filter unit sidewall &Sec. Clarifier 2 launder weir wall form work in progress..Mechanical erection and Painting progress... Kollam Project HD
13 Nov 2023 Civil works - RCC works - 26 out of 35 components -100 percent completed... 22 out of 32 items electromechanical supplied ..Cable trench sand laying progress... painting and mechanical erection progress... Kollam Project HD