| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Jun 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Drainage cover slab (near sludge shed) shuttering work in progress... | Kollam Project HD | |
| 04 Jun 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site......Drainage slab (near air blower building) reinforcement work in progress... | Kollam Project HD | |
| 03 Jun 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site......Drainage slab (near air blower building) shuttering work in progress | Kollam Project HD | |
| 01 Jun 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site......Admin building column deshuttering works in progress... | Kollam Project HD | |
| 31 May 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site...Admin building column concrete work in progress.. | Kollam Project HD | |
| 30 May 2024 | No work due to rain | Kollam Project HD | |
| 29 May 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site...CCT and Sec.Clarifier 2 handrail finishing works in progress.. | Kollam Project HD | |
| 28 May 2024 | No work due to heavy rain | Kollam Project HD | |
| 27 May 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site...CCT and Sec.Clarifier 2 handrail finishing works in progress...Cleaning and levelling work in progress... | Kollam Project HD | |
| 25 May 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site...CCT and Sec.Clarifier 2 handrail finishing works in progress...Admin building column second lift form work in progress... | Kollam Project HD |