Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Nov 2024 Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 84.3% (27 numbers supplied & installed) Electrical Works 90% .. Kollam Project HD
04 Nov 2024 Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 84.3% (27 numbers supplied & installed) Electrical Works 90% .. Kollam Project HD
02 Nov 2024 Project Status Updation Update status Last updation Work in progress | 90% Completed | 19/10/2024 Civil Works: Overall 7% RCC works pending, with 195 m3 of RCC works pending ( 195m3 for Admin Building). Total number of RCC structures/Buildings = 35. 34 components 90% completed, 1 -admin building -28% completed. Electromechanical Works: 16% supply (5)pending out of 32 numbers of EM components. 27 no.s arrived at the site, 1 no.s in transit to the site. 5 no.s inspections pending. 19% Installation works pending . Kollam Project HD
01 Nov 2024 Project Status Updation Update status Last updation Work in progress | 90% Completed | 19/10/2024 Civil Works: Overall 7% RCC works pending, with 195 m3 of RCC works pending ( 195m3 for Admin Building). Total number of RCC structures/Buildings = 35. 34 components 90% completed, 1 -admin building -28% completed. Electromechanical Works: 16% supply (5)pending out of 32 numbers of EM components. 27 no.s arrived at the site, 1 no.s in transit to the site. 5 no.s inspections pending. 19% Installation works pending . Kollam Project HD
22 Oct 2024 Project Status Updation Update status Last updation Work in progress | 90% Completed | 19/10/2024 Civil Works: Overall 7% RCC works pending, with 195 m3 of RCC works pending ( 195m3 for Admin Building). Total number of RCC structures/Buildings = 35. 34 components 90% completed, 1 -admin building -28% completed. Electromechanical Works: 16% supply (5)pending out of 32 numbers of EM components. 27 no.s arrived at the site, 1 no.s in transit to the site. 5 no.s inspections pending. 19% Installation works pending . Kollam Project HD
21 Oct 2024 Project Status Updation Update status Last updation Work in progress | 90% Completed | 19/10/2024 Civil Works: Overall 8% RCC works pending, with 195 m3 of RCC works pending ( 195m3 for Admin Building). Total number of RCC structures/Buildings = 35. 34 components 90% completed, 1 -admin building -28% completed. Electromechanical Works: 18% supply (6)pending out of 32 numbers of EM components. 26 no.s arrived at the site, 2 no.s in transit to the site. 4 no.s inspections pending. 30% Installation works pending (22 out of 24 supplied installed). Kollam Project HD
19 Oct 2024 Civil Works: Overall 8% RCC works pending, with 195 m3 of RCC works pending ( 195m3 for Admin Building). Total number of RCC structures/Buildings = 35. 34 components 90% completed, 1 -admin building -28% completed. Electromechanical Works: 18% supply (6)pending out of 32 numbers of EM components. 26 no.s arrived at the site, 2 no.s in transit to the site. 4 no.s inspections pending. 30% Installation works pending (22 out of 24 supplied installed).   Kollam Project HD
17 Oct 2024 pending 10 % works ( Civil- 8%; EM Supply - 19% ; Installation - 30% ) Kollam Project HD
14 Oct 2024 pending 10 % works ( Civil- 8%; EM Supply - 19% ; Installation - 35% ) Kollam Project HD
09 Oct 2024 Pending 10 % works ( Civil works -8%, EM supply works -21% ; EM installation works - 37.5% ) Kollam Project HD