| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Nov 2024 | Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 84.3% (27 numbers supplied & installed) Electrical Works 90% .. | Kollam Project HD | |
| 04 Nov 2024 | Civil Works 35 RCC structures 93% Electromechanical Works 32 EM components 84.3% (27 numbers supplied & installed) Electrical Works 90% .. | Kollam Project HD | |
| 02 Nov 2024 | Project Status Updation Update status Last updation Work in progress | 90% Completed | 19/10/2024 Civil Works: Overall 7% RCC works pending, with 195 m3 of RCC works pending ( 195m3 for Admin Building). Total number of RCC structures/Buildings = 35. 34 components 90% completed, 1 -admin building -28% completed. Electromechanical Works: 16% supply (5)pending out of 32 numbers of EM components. 27 no.s arrived at the site, 1 no.s in transit to the site. 5 no.s inspections pending. 19% Installation works pending . | Kollam Project HD | |
| 01 Nov 2024 | Project Status Updation Update status Last updation Work in progress | 90% Completed | 19/10/2024 Civil Works: Overall 7% RCC works pending, with 195 m3 of RCC works pending ( 195m3 for Admin Building). Total number of RCC structures/Buildings = 35. 34 components 90% completed, 1 -admin building -28% completed. Electromechanical Works: 16% supply (5)pending out of 32 numbers of EM components. 27 no.s arrived at the site, 1 no.s in transit to the site. 5 no.s inspections pending. 19% Installation works pending . | Kollam Project HD | |
| 22 Oct 2024 | Project Status Updation Update status Last updation Work in progress | 90% Completed | 19/10/2024 Civil Works: Overall 7% RCC works pending, with 195 m3 of RCC works pending ( 195m3 for Admin Building). Total number of RCC structures/Buildings = 35. 34 components 90% completed, 1 -admin building -28% completed. Electromechanical Works: 16% supply (5)pending out of 32 numbers of EM components. 27 no.s arrived at the site, 1 no.s in transit to the site. 5 no.s inspections pending. 19% Installation works pending . | Kollam Project HD | |
| 21 Oct 2024 | Project Status Updation Update status Last updation Work in progress | 90% Completed | 19/10/2024 Civil Works: Overall 8% RCC works pending, with 195 m3 of RCC works pending ( 195m3 for Admin Building). Total number of RCC structures/Buildings = 35. 34 components 90% completed, 1 -admin building -28% completed. Electromechanical Works: 18% supply (6)pending out of 32 numbers of EM components. 26 no.s arrived at the site, 2 no.s in transit to the site. 4 no.s inspections pending. 30% Installation works pending (22 out of 24 supplied installed). | Kollam Project HD | |
| 19 Oct 2024 | Civil Works: Overall 8% RCC works pending, with 195 m3 of RCC works pending ( 195m3 for Admin Building). Total number of RCC structures/Buildings = 35. 34 components 90% completed, 1 -admin building -28% completed. Electromechanical Works: 18% supply (6)pending out of 32 numbers of EM components. 26 no.s arrived at the site, 2 no.s in transit to the site. 4 no.s inspections pending. 30% Installation works pending (22 out of 24 supplied installed). | Kollam Project HD | |
| 17 Oct 2024 | pending 10 % works ( Civil- 8%; EM Supply - 19% ; Installation - 30% ) | Kollam Project HD | |
| 14 Oct 2024 | pending 10 % works ( Civil- 8%; EM Supply - 19% ; Installation - 35% ) | Kollam Project HD | |
| 09 Oct 2024 | Pending 10 % works ( Civil works -8%, EM supply works -21% ; EM installation works - 37.5% ) | Kollam Project HD |