| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 … for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progresseived for electrical items - 2 out of 3 received at site...Centrifuge building handrail work in progress...Admin building column form work in progress... | Kollam Project HD | |
| 16 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 31 out 35 … for electromechanical items - 23 out of 32 items received .Cable tray work(support) in progresseived for electrical items - 2 out of 3 received at site...Clarifier 1- Handrail works in progress...painting progress... | Kollam Project HD | |
| 15 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 31 out 35 … for electromechanical items - 23 out of 32 items received .Cable tray work(support) in progresseived for electrical items - 2 out of 3 received at site...Painting and Earth levelling progress... | Kollam Project HD | |
| 13 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 31 out 35 … for electromechanical items - 23 out of 32 items received .Cable tray work(support) in progresseived for electrical items - 2 out of 3 received at site...MBBR 3 handrail gap filling work in progress...Earth levelling and Painting progress... | Kollam Project HD | |
| 12 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 31 out 35 … for electromechanical items - 23 out of 32 items received .Cable tray work(support) in progresseived for electrical items - 2 out of 3 received at site..Septage tank lifting chain fixing work in progress... Earth levelling and painting progress... | Kollam Project HD | |
| 11 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 31 out 35 … for electromechanical items - 23 out of 32 items received .Cable tray work(support) in progresseived for electrical items - 2 out of 3 received at site..Earth levelling and Painting progress... | Kollam Project HD | |
| 10 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 31 out 35 … for electromechanical items - 23 out of 32 items received .Cable tray work(support) in progresseived for electrical items - 2 out of 3 received at site..Earth levelling and Painting progress... | Kollam Project HD | |
| 09 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 31 out 35 … for electromechanical items - 23 out of 32 items received .Cable tray work(support) in progresseived for electrical items - 2 out of 3 received at site...MBBR 2 lifting chain & guide wire fixing work in progress...Painting and earth levelling progress... | Kollam Project HD | |
| 08 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 31 out 35 … for electromechanical items - 23 out of 32 items received .Cable tray work(support) in progresseived for electrical items - 2 out of 3 received at site...Air blower header clamp fixing work in progress...Site cleaning and earth levelling progress... | Kollam Project HD | |
| 06 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 31 out 35 … for electromechanical items - 23 out of 32 items received .Cable tray work(support) in progresseived for electrical items - 2 out of 3 received at site...Electric cable tray work in progress...Centrifuge feed pump Pipe line work in progress...Site cleaning and mechanical works in progress... | Kollam Project HD |