| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 07 Oct 2024 | Pending Works as on October 4, 2024: Preliminary Treatment Unit Septage Tank: Septage tank agitator not supplied. Septage Pump House: Odour control system not supplied, door, window, electric connection facilities/motor pending. Inlet Chamber: Sewer line pipe, sluice gate (8 nos) installation work pending, minor concrete finishing work, walkway plastering, and chequered tile work. CBSC & FBSC: Finishing work pending. Grit Chamber: Floor epoxy paint work, partial flume installation, walkway plastering, and chequered tile work pending. Equalization Tank: Pump lifting arrangement pending. MBBR 1: Media filling, pump lifting arrangement, chequered plate/access way installation pending. MBBR 2-4: Media filling, pump lifting arrangement, chequered plate/access way installation pending. Secondary Treatment S. Clarifier No. 1: Floor epoxy paint, screed concrete, clarifier bridge painting work, access way between clarifiers 1 and 2, handrail second coat painting work pending. S. Clarifier No. 2: Similar to S. Clarifier No. 1, Other Components CCT: 500 mm pipe laying pending from CCT to aerator, step/access way from clarifier 1 to CCT, handrail second coat painting work pending. Aerator: Outlet pipe connection to Ashtamudi Lake pending. Chlorination Room: Chlorine dosing pump and system not supplied, shed/enclosure construction, electrical connection/wiring pending. Sludge Holding Tank: Ladder/stair installation pending. Sludge Pump House: Door, window, electric connection pending. Filtrate Cum Thickened Pump House: Pump room waterproofing work pending. Centrifuge Building: Handrail second coat painting, equipment installation (Poly Electrolyte Tank, dosing pump, electric hoist not supplied). Sludge Drying Bed: Rotary sludge dryer not supplied, finishing work pending. Sludge Shed: Flooring, painting finishing work, electrical connection/wiring pending. Air Blower Room: Painting work (inner wall), electrical connection/wiring pending. MCC Room: Rolling shutter installation, window, and electric connection facilities pending. Transformer Room: Rolling shutter, electric cable arrangement, connection facilities, ramp work pending. Additional Works DG Platform: Shed/enclosure construction pending. Security Cabin: Lintel work, electric connection facilities, toilet installation pending. Administrative Building: Ground floor columns completed; bottom slab work in progress; all other works pending. Internal Roads and Landscaping: Storm outlet, landscape (fixing curbs, planting grass/shrubs, etc.), road side interlock not supplied, road tarring second coat, and interlock work pending. External Site Works: Front gate painting, emblem fixing, site cleaning, manhole cover/chequered plate installation pending. Electromechanical Works: Poly Electrolyte Tank with agitator, chlorination system, HOT/chain pulley block, odour control at septage tank, rotary sludge dryer, lab equipment, and supply of furniture pending. | Kollam Project HD | |
| 04 Oct 2024 | Review meeting by SE, PHC - as the Hon. Minister of LSGD has instructed the completion of all works at the Kureepuzha STP site by the end of October 2024, with the planned inauguration on November 1, 2024 and remarked the importance & urgency in sticking on the completion time. Contractor to submit a detailed schedule for completion trial run and inauguration Electrical work to start within two days, and efforts should be made to complete it within three weeks. Administrative building work and lab setup to begin immediately. Obtain electrical approvals without delay. | Kollam Project HD | |
| 28 Sep 2024 | work is progressing slow | Kollam Project HD | |
| 25 Sep 2024 | (25th September 2024) - review meeting by SE, PHC Kollam The Chair reminded the contractor of the key actions discussed in the previous meeting. such as: Expediting power supply and electrical connections by October 15, 2024. Arranging pre-inspection for electrical inspection compliance. Completing all remaining civil, piping, and electrical works by the set deadlines. Supplying and installing pending electromechanical items (e.g., septage tank agitator, chlorination system, rotary sludge dryer). Beautification works to be completed before the inauguration. | Kollam Project HD | |
| 18 Sep 2024 | Over all progress - 90% | Kollam Project HD | |
| 09 Sep 2024 | o Overall Progress: 90% completion. o Pending Work: The key issue is the lack of connection between the sewer network and the STP, which is crucial for operationalizing the plant. This could delay commissioning by at least two years. o Design Modifications: Due to a pending court case, the location of the control unit building was shifted, requiring modifications to the design for speedy completion. o Sewer Network: Not yet connected, which is a major hurdle for plant commissioning. • Civil Works: o Completed: 33 out of 35 RCC structures/buildings are 90% completed. o Pending: ▪ Admin Building: 28% completion. ▪ Security Room: structure completed. ▪ RCC Works: 195 m³ of RCC works remain, including 2.5 m³ for the security room and 195 m³ for the admin building. • Electromechanical Works: o Supply: 22% of items pending delivery (7 out of 32 components). o Installation: 37.5% of installations pending (20 out of 24 supplied components). o Factory Inspections: 26 out of 27 inspections completed; however, six more inspections are pending. | Kollam Project HD | |
| 08 Sep 2024 | o Overall Progress: 90% completion. o Pending Work: The key issue is the lack of connection between the sewer network and the STP, which is crucial for operationalizing the plant. This could delay commissioning by at least two years. o Design Modifications: Due to a pending court case, the location of the control unit building was shifted, requiring modifications to the design for speedy completion. o Sewer Network: Not yet connected, which is a major hurdle for plant commissioning. • Civil Works: o Completed: 33 out of 35 RCC structures/buildings are 90% completed. o Pending: ▪ Admin Building: 28% completion. ▪ Security Room: Not started. ▪ RCC Works: 198 m³ of RCC works remain, including 2.5 m³ for the security room and 195 m³ for the admin building. • Electromechanical Works: o Supply: 22% of items pending delivery (7 out of 32 components). o Installation: 37.5% of installations pending (20 out of 24 supplied components). o Factory Inspections: 26 out of 27 inspections completed; however, six more inspections are pending. | Kollam Project HD | |
| 07 Sep 2024 | o Overall Progress: 90% completion. o Pending Work: The key issue is the lack of connection between the sewer network and the STP, which is crucial for operationalizing the plant. This could delay commissioning by at least two years. o Design Modifications: Due to a pending court case, the location of the control unit building was shifted, requiring modifications to the design for speedy completion. o Sewer Network: Not yet connected, which is a major hurdle for plant commissioning. • Civil Works: o Completed: 33 out of 35 RCC structures/buildings are 90% completed. o Pending: ▪ Admin Building: 28% completion. ▪ Security Room: Not started. ▪ RCC Works: 198 m³ of RCC works remain, including 2.5 m³ for the security room and 195 m³ for the admin building. • Electromechanical Works: o Supply: 22% of items pending delivery (7 out of 32 components). o Installation: 37.5% of installations pending (20 out of 24 supplied components). o Factory Inspections: 26 out of 27 inspections completed; however, six more inspections are pending. | Kollam Project HD | |
| 06 Sep 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 26 out of 32 items received and for electrical items - 3 out of 3 received at site....Security room roof slab reinforcement work in progress... | Kollam Project HD | |
| 05 Sep 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 26 out of 32 items received and for electrical items - 3 out of 3 received at site....Security room roof slab reinforcement work in progress... | Kollam Project HD |