Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 May 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site...Admin building column reinforcement work in progress... Kollam Project HD
23 May 2024 No work due to heavy rain Kollam Project HD
22 May 2024 No work due to heavy rain Kollam Project HD
21 May 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site.....Mechanical works,Site cleaning progress... Kollam Project HD
18 May 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Road tarring and cleaning progress...Mechanical works in progress... Kollam Project HD
17 May 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Road works and Handrail works in progress... Kollam Project HD
16 May 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site...Admin building column concrete work in progress...Admin staircase concrete work in progress...CCT handrail work in progress... Kollam Project HD
15 May 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site... CCT-Handrail works in progress....Admin building staircase form work in progress... Kollam Project HD
14 May 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site... Admin building column form work and staircase reinforcement work in progress...Sec.Clarifier 2- handrail work in progress...Admin building column Curing work in progress... Kollam Project HD
13 May 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Admin building staircase form work in progress....Sec.Clarifier 1 handrail work in progress... Kollam Project HD