| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 29 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site...Site cleaning and earth levelling progress...Admin building column form work and steel making progress... | Kollam Project HD | |
| 27 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Admin building column form work and steel making progress...Earth levelling progress... | Kollam Project HD | |
| 26 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site.,,Steel making work in progress (for admin building)..Earth levelling works in progress.. | Kollam Project HD | |
| 25 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site.,,Steel making work in progress (for admin building)..Earth levelling works in progress.. | Kollam Project HD | |
| 24 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site...Earth levelling works in progress..Admin building column reinforcement work in progress.... | Kollam Project HD | |
| 23 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Sec.Clarifier 1...Handrail works in progress...Admin building column reinforcement work in progress.. | Kollam Project HD | |
| 22 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 … for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progresseived for electrical items - 2 out of 3 received at site....Sec.Clarifier 1...Handrail works in progress...Admin building column reinforcement work in progress.... | Kollam Project HD | |
| 20 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 … for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progresseived for electrical items - 2 out of 3 received at site....Admin building column form work in progress.....Mechanical work in progress.. | Kollam Project HD | |
| 19 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 … for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progresseived for electrical items - 2 out of 3 received at site....Admin building column form work in progress.....Secondary clarifier 1.. and Centrifuge building mechanical works in progress... | Kollam Project HD | |
| 18 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 … for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progresseived for electrical items - 2 out of 3 received at site....Admin building column form work in progress.....Secondary clarifier 1.. and Centrifuge building mechanical works in progress... | Kollam Project HD |