29 Apr 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site...Site cleaning and earth levelling progress...Admin building column form work and steel making progress... Kollam Project HD
27 Apr 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Admin building column form work and steel making progress...Earth levelling progress... Kollam Project HD
26 Apr 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site.,,Steel making work in progress (for admin building)..Earth levelling works in progress.. Kollam Project HD
25 Apr 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site.,,Steel making work in progress (for admin building)..Earth levelling works in progress.. Kollam Project HD
24 Apr 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site...Earth levelling works in progress..Admin building column reinforcement work in progress.... Kollam Project HD
23 Apr 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Sec.Clarifier 1...Handrail works in progress...Admin building column reinforcement work in progress.. Kollam Project HD
22 Apr 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 … for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progresseived for electrical items - 2 out of 3 received at site....Sec.Clarifier 1...Handrail works in progress...Admin building column reinforcement work in progress.... Kollam Project HD
20 Apr 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 … for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progresseived for electrical items - 2 out of 3 received at site....Admin building column form work in progress.....Mechanical work in progress.. Kollam Project HD
19 Apr 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 … for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progresseived for electrical items - 2 out of 3 received at site....Admin building column form work in progress.....Secondary clarifier 1.. and Centrifuge building mechanical works in progress... Kollam Project HD
18 Apr 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 … for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progresseived for electrical items - 2 out of 3 received at site....Admin building column form work in progress.....Secondary clarifier 1.. and Centrifuge building mechanical works in progress... Kollam Project HD