| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Sep 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 26 out of 32 items received and for electrical items - 3 out of 3 received at site....Security room roof slab reinforcement work in progress... | Kollam Project HD | |
| 03 Sep 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 26 out of 32 items received and for electrical items - 3 out of 3 received at site....Security room roof slab form work and reinforcement work in progress... | Kollam Project HD | |
| 22 Jul 2024 | For First Package : 12 MLD STP - Overall 90% completed , Civil works - 92% completed , Electromechanical supply - 78% completed , Installation - 65% completed ; Electrical works - 90% Completed.... package 2 - 50 KLD FSTP - Work retendered. | Kollam Project HD | |
| 25 Jun 2024 | For First Package : 12 MLD STP - Overall 90% completed , Civil works - 92% completed , Electromechanical supply - 78% completed , Installation - 65% completed ; Electrical works - 90% Completed.... package 2 - 50 KLD FSTP - under tender stage | Kollam Project HD | |
| 24 Jun 2024 | Finishing work in progress.... | Kollam Project HD | |
| 22 Jun 2024 | Finishing work in progress.... | Kollam Project HD | |
| 21 Jun 2024 | Finishing work in progress.... | Kollam Project HD | |
| 20 Jun 2024 | No work due to rain | Kollam Project HD | |
| 19 Jun 2024 | No work due to rain | Kollam Project HD | |
| 18 Jun 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 25 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site..- Security room foundation excavation work in progress... | Kollam Project HD |