Status Date Overall Project Status Project Officer Contact
04 Sep 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 26 out of 32 items received and for electrical items - 3 out of 3 received at site....Security room roof slab reinforcement work in progress... Kollam Project HD
03 Sep 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 26 out of 32 items received and for electrical items - 3 out of 3 received at site....Security room roof slab form work and reinforcement work in progress... Kollam Project HD
22 Jul 2024 For First Package : 12 MLD STP - Overall 90% completed , Civil works - 92% completed , Electromechanical supply - 78% completed , Installation - 65% completed ; Electrical works - 90% Completed.... package 2 - 50 KLD FSTP - Work retendered. Kollam Project HD
25 Jun 2024 For First Package : 12 MLD STP - Overall 90% completed , Civil works - 92% completed , Electromechanical supply - 78% completed , Installation - 65% completed ; Electrical works - 90% Completed.... package 2 - 50 KLD FSTP - under tender stage Kollam Project HD
24 Jun 2024 Finishing work in progress.... Kollam Project HD
22 Jun 2024 Finishing work in progress.... Kollam Project HD
21 Jun 2024 Finishing work in progress.... Kollam Project HD
20 Jun 2024 No work due to rain Kollam Project HD
19 Jun 2024 No work due to rain Kollam Project HD
18 Jun 2024 RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 25 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site..- Security room foundation excavation work in progress... Kollam Project HD