| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 May 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Centrifuge building handrail work in progress..Admin building column form work in progress... | Kollam Project HD | |
| 10 May 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Admin building second lift column rcc work in progress ...Centrifuge building handrail work in progress...Drainage slab ready for concrete.... | Kollam Project HD | |
| 09 May 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Admin building second lift 9 column form work completed..Ready for concrete..Admin building floor levelling and staircase form work in progress..... | Kollam Project HD | |
| 08 May 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Admin building second lift 9 column form work completed..Ready for concrete..Cable trench Slab deshuttering work in progress...Drainage slab form work in progress.... | Kollam Project HD | |
| 07 May 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Admin building column 2nd lift reinforcement & form work in progress.. | Kollam Project HD | |
| 06 May 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Admin building column 2nd lift reinforcement & form work in progress...Earth levelling progress... | Kollam Project HD | |
| 04 May 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site..Admin building column concrete work in progress.. | Kollam Project HD | |
| 03 May 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site...Earth levelling works in progress... | Kollam Project HD | |
| 02 May 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site...Site cleaning and earth levelling progress...Admin building steel making progress...MBBR 1 cleaning work in progress... | Kollam Project HD | |
| 30 Apr 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site...Site cleaning and earth levelling progress...Admin building steel making progress... | Kollam Project HD |