| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 Jun 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 25 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site..- Security room foundation excavation and Steel making works in progress... | Kollam Project HD | |
| 15 Jun 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 25 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site..- ground leveling progress ... | Kollam Project HD | |
| 14 Jun 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 25 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site...Security room - setting out work and ground leveling progress ... | Kollam Project HD | |
| 13 Jun 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site...Ground leveling progress ... | Kollam Project HD | |
| 12 Jun 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site...Ground leveling progress and material shifting for admin building roof slab work. | Kollam Project HD | |
| 11 Jun 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site...Ground leveling progress and material shifting for admin building roof slab work. | Kollam Project HD | |
| 10 Jun 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site...Ground leveling progress... | Kollam Project HD | |
| 08 Jun 2024 | No work, due to rain | Kollam Project HD | |
| 07 Jun 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Earth cleaning and levelling progress.... | Kollam Project HD | |
| 06 Jun 2024 | RCC WORKS pending for admin building and other RCC works completed 34 out 35 ( Admin building- 28% completed … other civil structures - finishing works in progress)… for electromechanical items - 24 out of 32 items received .Cable tray work(support) in progress and for electrical items - 2 out of 3 received at site....Earth cleaning and levelling progress.... | Kollam Project HD |