Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Dec 2025 Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1153nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1679 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5524 nos FHTCs are completed. Total Pipe laid till date-12000 m Kollam WS Sn 2 - AE
29 Dec 2025 Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1153nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1679 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5524 nos FHTCs are completed. Total Pipe laid till date-12000 m Kollam WS Sn 2 - AE
26 Dec 2025 Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1153nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1679 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5524 nos FHTCs are completed. Total Pipe laid till date-12000 m Kollam WS Sn 2 - AE
22 Dec 2025 Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1153nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1679 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5524 nos FHTCs are completed. Total Pipe laid till date-12000 m Kollam WS Sn 2 - AE
19 Dec 2025 Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1153nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1679 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5524 nos FHTCs are completed. Total Pipe laid till date-12000 m Kollam WS Sn 2 - AE
06 Dec 2025 Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1153nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1679 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5499 nos FHTCs are completed. Total Pipe laid till date-12000 m Kollam WS Sn 2 - AE
02 Dec 2025 Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1153nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1679 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5450 nos FHTCs are completed. Total Pipe laid till date-12000 m Kollam WS Sn 2 - AE
22 Nov 2025 Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1140nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1679 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5416 nos FHTCs are completed. Total Pipe laid till date-12000 m Kollam WS Sn 2 - AE
18 Nov 2025 Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1140nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1656 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5416 nos FHTCs are completed. Total Pipe laid till date-12000 m Kollam WS Sn 2 - AE
05 Nov 2025 Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1140nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1648 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5380 nos FHTCs are completed. Total Pipe laid till date-12000 m Kollam WS Sn 2 - AE