| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 31 Dec 2025 | Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1153nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1679 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5524 nos FHTCs are completed. Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE | |
| 29 Dec 2025 | Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1153nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1679 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5524 nos FHTCs are completed. Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE | |
| 26 Dec 2025 | Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1153nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1679 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5524 nos FHTCs are completed. Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE | |
| 22 Dec 2025 | Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1153nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1679 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5524 nos FHTCs are completed. Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE | |
| 19 Dec 2025 | Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1153nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1679 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5524 nos FHTCs are completed. Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE | |
| 06 Dec 2025 | Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1153nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1679 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5499 nos FHTCs are completed. Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE | |
| 02 Dec 2025 | Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1153nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1679 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5450 nos FHTCs are completed. Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE | |
| 22 Nov 2025 | Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1140nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1679 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5416 nos FHTCs are completed. Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE | |
| 18 Nov 2025 | Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1140nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1656 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5416 nos FHTCs are completed. Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE | |
| 05 Nov 2025 | Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1140nos FHTCs are given,Total Pipe laid till date-12983m (Work in progress)delay due to water clogging. Package-3- Sakthikulangara & Thrikkadavoor zone - 83 % completed ,1648 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5380 nos FHTCs are completed. Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE |