| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 18 Apr 2026 | Package-3- Old Muncipal area in Kollam corporation - 95% completed, 1339 nos FHTCs are given,Total Pipe laid till date-13677.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 89 % completed ,1938 nos FHTCs are given, Total Pipe laid till date- 14835.5 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing.---- . Package1 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m | Kollam WS Sn 2 - AE | |
| 13 Apr 2026 | Package-3- Old Muncipal area in Kollam corporation - 95% completed, 1263nos FHTCs are given,Total Pipe laid till date-13392.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 89 % completed ,1938 nos FHTCs are given, Total Pipe laid till date- 14835.5 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing.---- . Package1 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m | Kollam WS Sn 2 - AE | |
| 08 Apr 2026 | Package-3- Old Muncipal area in Kollam corporation - 95% completed, 1263nos FHTCs are given,Total Pipe laid till date-13392.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 89 % completed ,1938 nos FHTCs are given, Total Pipe laid till date- 14835.5 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing.------------- . Package1 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m | Kollam WS Sn 2 - AE | |
| 04 Apr 2026 | Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1263nos FHTCs are given,Total Pipe laid till date-13392.1m Work is ongoing. Package-3- Sakthikulangara & Thrikkadavoor zone - 88 % completed ,1922 nos FHTCs are given, Total Pipe laid till date- 14835.5 m(laying completed), FHTC works is ongoing. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m | Kollam WS Sn 2 - AE | |
| 30 Mar 2026 | Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1263nos FHTCs are given,Total Pipe laid till date-13392.1m Work is ongoing. Package-3- Sakthikulangara & Thrikkadavoor zone - 88 % completed ,1922 nos FHTCs are given, Total Pipe laid till date- 14835.5 m(laying completed), FHTC works is ongoing. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m | Kollam WS Sn 2 - AE | |
| 23 Mar 2026 | Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1263nos FHTCs are given,Total Pipe laid till date-13392.1m Work is ongoing. Package-3- Sakthikulangara & Thrikkadavoor zone - 88 % completed ,1880 nos FHTCs are given, Total Pipe laid till date- 14835.5 m(laying completed), FHTC works is ongoing. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5726 nos FHTCs are completed. Total Pipe laid till date-13617.5 m | Kollam WS Sn 2 - AE | |
| 17 Mar 2026 | Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1263nos FHTCs are given,Total Pipe laid till date-13392.1m Work is ongoing. Package-3- Sakthikulangara & Thrikkadavoor zone - 88 % completed ,1869 nos FHTCs are given, Total Pipe laid till date- 14835.5 m(laying completed), FHTC works is ongoing. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5679 nos FHTCs are completed. Total Pipe laid till date-13617.5 m | Kollam WS Sn 2 - AE | |
| 13 Mar 2026 | Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1263nos FHTCs are given,Total Pipe laid till date-13392.1m Work is ongoing. Package-3- Sakthikulangara & Thrikkadavoor zone - 88 % completed ,1869 nos FHTCs are given, Total Pipe laid till date- 14835.5 m(laying completed), FHTC works is ongoing. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5612 nos FHTCs are completed. Total Pipe laid till date-13473.6 m | Kollam WS Sn 2 - AE | |
| 07 Mar 2026 | Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1263nos FHTCs are given,Total Pipe laid till date-13392.1m Work is ongoing. Package-3- Sakthikulangara & Thrikkadavoor zone - 88 % completed ,1869 nos FHTCs are given, Total Pipe laid till date- 14835.5 m(laying completed), FHTC works is ongoing. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5612 nos FHTCs are completed. Total Pipe laid till date-13473.6 m | Kollam WS Sn 2 - AE | |
| 03 Mar 2026 | Package-1- Old Muncipal area in Kollam corporation - 92% completed, 1263nos FHTCs are given,Total Pipe laid till date-13392.1m Work is ongoing. Package-3- Sakthikulangara & Thrikkadavoor zone - 88 % completed ,1869 nos FHTCs are given, Total Pipe laid till date- 14835.5 m(laying completed), FHTC works is ongoing. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5612 nos FHTCs are completed. Total Pipe laid till date-13473.6 m | Kollam WS Sn 2 - AE |