Status Date Overall Project Status Project Officer Contact
13 Jul 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1452 nos FHTCs are given,Total Pipe laid till date-13825.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 92 % completed ,2085 nos FHTCs are given, Total Pipe laid till date- 15727.8 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, heavy rain and water logging cause slight delay in work . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5806 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
03 Jul 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1452 nos FHTCs are given,Total Pipe laid till date-13825.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 92 % completed ,2085 nos FHTCs are given, Total Pipe laid till date- 15727.8 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, heavy rain and water logging cause slight delay in work . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5806 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
27 Jun 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1400 nos FHTCs are given,Total Pipe laid till date-13677.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 91 % completed ,2050 nos FHTCs are given, Total Pipe laid till date- 15727.8 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, heavy rain and water logging cause slight delay in work . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
20 Jun 2026 ackage-1- Old Muncipal area in Kollam corporation - 95% completed, 1400 nos FHTCs are given,Total Pipe laid till date-13677.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 91 % completed ,2035 nos FHTCs are given, Total Pipe laid till date- 15727.8 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, heavy rain and water logging cause slight delay in work . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
16 Jun 2026 ackage-1- Old Muncipal area in Kollam corporation - 95% completed, 1400 nos FHTCs are given,Total Pipe laid till date-13677.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 91 % completed ,2035 nos FHTCs are given, Total Pipe laid till date- 15727.8 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, heavy rain and water logging cause slight delay in work . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
12 Jun 2026 ackage-1- Old Muncipal area in Kollam corporation - 95% completed, 1400 nos FHTCs are given,Total Pipe laid till date-13677.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 91 % completed ,2035 nos FHTCs are given, Total Pipe laid till date- 15727.8 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, heavy rain and water logging cause slight delay in work . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
09 Jun 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1400 nos FHTCs are given,Total Pipe laid till date-13677.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 91 % completed ,2035 nos FHTCs are given, Total Pipe laid till date- 15727.8 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing.---- . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
02 Jun 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1400 nos FHTCs are given,Total Pipe laid till date-13677.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 91 % completed ,2035 nos FHTCs are given, Total Pipe laid till date- 15727.8 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing.---- . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
19 May 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1400 nos FHTCs are given,Total Pipe laid till date-13677.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 91 % completed ,2035 nos FHTCs are given, Total Pipe laid till date- 15727.8 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing.---- . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
11 May 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1400 nos FHTCs are given,Total Pipe laid till date-13677.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 91 % completed ,2035 nos FHTCs are given, Total Pipe laid till date- 15727.8 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing.---- . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE