| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Aug 2025 | Package-1- Old Muncipal area in Kollam corporation - 81 % completed, 993nos FHTCs are given,Total Pipe laid till date-11433.5m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1621 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5182nos FHTCs are completed. Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE | |
| 18 Aug 2025 | Package-1- Old Muncipal area in Kollam corporation - 81 % completed, 993nos FHTCs are given,Total Pipe laid till date-11433.5m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5182nos FHTCs are completed. Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE | |
| 11 Aug 2025 | Package-1- Old Muncipal area in Kollam corporation - 81 % completed, 993nos FHTCs are given,Total Pipe laid till date-11433.5m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5182nos FHTCs are completed. Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE | |
| 04 Aug 2025 | Package-1- Old Muncipal area in Kollam corporation - 81 % completed, 993nos FHTCs are given,Total Pipe laid till date-11433.5m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5170nos FHTCs are completed. Total Pipe laid till date-12000 m | Kollam WS Sn 2 - AE | |
| 01 Aug 2025 | Package-1- Old Muncipal area in Kollam corporation - 81 % completed, 993nos FHTCs are given,Total Pipe laid till date-11433.5m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5170nos FHTCs are completed. Total Pipe laid till date-12000 m. | Kollam WS Sn 2 - AE | |
| 28 Jul 2025 | Package-1- Old Muncipal area in Kollam corporation - 81 % completed, 993nos FHTCs are given,Total Pipe laid till date-11433.5m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5170nos FHTCs are completed. Total Pipe laid till date-12000 m. | Kollam WS Sn 2 - AE | |
| 25 Jul 2025 | Package-1- Old Muncipal area in Kollam corporation - 81 % completed, 993nos FHTCs are given,Total Pipe laid till date-11433.5m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5170nos FHTCs are completed. Total Pipe laid till date-12000 m. | Kollam WS Sn 2 - AE | |
| 23 Jul 2025 | Package-1- Old Muncipal area in Kollam corporation - 81 % completed, 993nos FHTCs are given,Total Pipe laid till date-11433.5m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5160nos FHTCs are completed. Total Pipe laid till date-12000 m. | Kollam WS Sn 2 - AE | |
| 18 Jul 2025 | Package-1- Old Muncipal area in Kollam corporation - 81 % completed, 993nos FHTCs are given,Total Pipe laid till date-11433.5m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5160nos FHTCs are completed. Total Pipe laid till date-12000 m. | Kollam WS Sn 2 - AE | |
| 14 Jul 2025 | Package-1- Old Muncipal area in Kollam corporation - 77 % completed, 956 nos FHTCs are given,Total Pipe laid till date-10805.6m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5160nos FHTCs are completed. Total Pipe laid till date-12000 m. | Kollam WS Sn 2 - AE |