Status Date Overall Project Status Project Officer Contact
21 Aug 2025 Package-1- Old Muncipal area in Kollam corporation - 81 % completed, 993nos FHTCs are given,Total Pipe laid till date-11433.5m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1621 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5182nos FHTCs are completed. Total Pipe laid till date-12000 m Kollam WS Sn 2 - AE
18 Aug 2025 Package-1- Old Muncipal area in Kollam corporation - 81 % completed, 993nos FHTCs are given,Total Pipe laid till date-11433.5m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5182nos FHTCs are completed. Total Pipe laid till date-12000 m Kollam WS Sn 2 - AE
11 Aug 2025 Package-1- Old Muncipal area in Kollam corporation - 81 % completed, 993nos FHTCs are given,Total Pipe laid till date-11433.5m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5182nos FHTCs are completed. Total Pipe laid till date-12000 m Kollam WS Sn 2 - AE
04 Aug 2025 Package-1- Old Muncipal area in Kollam corporation - 81 % completed, 993nos FHTCs are given,Total Pipe laid till date-11433.5m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5170nos FHTCs are completed. Total Pipe laid till date-12000 m Kollam WS Sn 2 - AE
01 Aug 2025 Package-1- Old Muncipal area in Kollam corporation - 81 % completed, 993nos FHTCs are given,Total Pipe laid till date-11433.5m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5170nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
28 Jul 2025 Package-1- Old Muncipal area in Kollam corporation - 81 % completed, 993nos FHTCs are given,Total Pipe laid till date-11433.5m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5170nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
25 Jul 2025 Package-1- Old Muncipal area in Kollam corporation - 81 % completed, 993nos FHTCs are given,Total Pipe laid till date-11433.5m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5170nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
23 Jul 2025 Package-1- Old Muncipal area in Kollam corporation - 81 % completed, 993nos FHTCs are given,Total Pipe laid till date-11433.5m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5160nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
18 Jul 2025 Package-1- Old Muncipal area in Kollam corporation - 81 % completed, 993nos FHTCs are given,Total Pipe laid till date-11433.5m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5160nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE
14 Jul 2025 Package-1- Old Muncipal area in Kollam corporation - 77 % completed, 956 nos FHTCs are given,Total Pipe laid till date-10805.6m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 79 % completed ,1604 nos FHTCs are given, Total Pipe laid till date- 12769.5 m(laying completed), FHTC works delaying due to conflict at Thuruth area for providing metered water connection. . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5160nos FHTCs are completed. Total Pipe laid till date-12000 m. Kollam WS Sn 2 - AE