Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 May 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1400 nos FHTCs are given,Total Pipe laid till date-13677.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 90 % completed ,2000 nos FHTCs are given, Total Pipe laid till date- 15727.8 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing.---- . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
02 May 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1400 nos FHTCs are given,Total Pipe laid till date-13677.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 89 % completed ,1958 nos FHTCs are given, Total Pipe laid till date- 15727.8 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing.---- . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
27 Apr 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1400 nos FHTCs are given,Total Pipe laid till date-13677.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 89 % completed ,1958 nos FHTCs are given, Total Pipe laid till date- 15727.8 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing.---- . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
27 Apr 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1339 nos FHTCs are given,Total Pipe laid till date-13677.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 89 % completed ,1958 nos FHTCs are given, Total Pipe laid till date- 15727.8 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing.---- . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
22 Apr 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1339 nos FHTCs are given,Total Pipe laid till date-13677.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 89 % completed ,1938 nos FHTCs are given, Total Pipe laid till date- 15727.8 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing.---- . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
22 Apr 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1339 nos FHTCs are given,Total Pipe laid till date-14569.4m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 89 % completed ,1938 nos FHTCs are given, Total Pipe laid till date- 14835.5 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing.---- . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
21 Apr 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1339 nos FHTCs are given,Total Pipe laid till date-13677.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 89 % completed ,1938 nos FHTCs are given, Total Pipe laid till date- 14835.5 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing.---- . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
21 Apr 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1339 nos FHTCs are given,Total Pipe laid till date-13677.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 89 % completed ,1938 nos FHTCs are given, Total Pipe laid till date- 14835.5 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing.---- . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
20 Apr 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1339 nos FHTCs are given,Total Pipe laid till date-13677.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 89 % completed ,1938 nos FHTCs are given, Total Pipe laid till date- 14835.5 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing.---- . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
18 Apr 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1339 nos FHTCs are given,Total Pipe laid till date-13677.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 89 % completed ,1938 nos FHTCs are given, Total Pipe laid till date- 14835.5 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing.---- . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5728 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE