| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 20 Sep 2023 | Package-1 pipe laying work ongoing, Package-2 pipe laying work ongoing, Package-3 pipe laying work ongoing. | Kollam WS Sn 3 - AE | |
| 18 Sep 2023 | Package -3. Pipe laying works ongoing, but due to heavy rain work progress is slow | Kollam WS Sn 2 - AE | |
| 18 Sep 2023 | Pipe laying works ongoing, but due to heavy rain work progress is slow | Kollam WS Sn 2 - AE | |
| 12 Sep 2023 | Package-3 -Pipe laying work under Sakthikulangara and Kadavoor continuous. | Kollam WS Sn 2 - AE | |
| 08 Sep 2023 | PAckage-1,Agreement executed on 04.07.2023, PAckage-2,Agreement executed on 07.07.2023, PAckage-3 pipe laying work under Sakthikulangara and Kadavoor temporarily stopped due to heavy rain. | Kollam WS Sn 2 - AE | |
| 08 Sep 2023 | PAckage-1,Agreement executed on 04.07.2023, PAckage-2,Agreement executed on 07.07.2023, PAckage-3 pipe laying work under Sakthikulangara and Kadavoor temporarily stopped due to heavy rain. | Kollam WS Sn 2 - AE | |
| 04 Sep 2023 | PAckage-1,Agreement executed on 04.07.2023, PAckage-2,Agreement executed on 07.07.2023, PAckage-3 pipe laying work under Sakthikulangara and Kadavoor temporarily stopped due to heavy rain. | Kollam WS Sn 2 - AE | |
| 24 Aug 2023 | PAckage-1,Agreement executed on 04.07.2023, PAckage-2,Agreement executed on 07.07.2023, PAckage-3 pipe laying work under Sakthikulangara and Kadavoor in progress | Kollam WS Sn 2 - AE | |
| 18 Aug 2023 | PAckage-1,Agreement executed on 04.07.2023, PAckage-2,Agreement executed on 07.07.2023, PAckage-3 pipe laying work under Sakthikulangara and Kadavoor in progress | Kollam WS Sn 2 - AE | |
| 17 Aug 2023 | PAckage-1,Agreement executed on 04.07.2023, PAckage-2,Agreement executed on 07.07.2023, PAckage-3 pipe laying work under Sakthikulangara and Kadavoor in progress | Kollam PH Dn EE |