Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 Dec 2023 23.66 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going. Palakkad Proj AE 3
05 Dec 2023 23.66 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going. Palakkad Proj AE 3
04 Dec 2023 23.66 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going. Palakkad Proj AE 3
02 Dec 2023 23.66 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going. Palakkad Proj AE 3
01 Dec 2023 23.66 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going. Palakkad Proj AE 3
30 Nov 2023 23.42 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going. Palakkad Proj AE 3
29 Nov 2023 23.02 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going. Palakkad Proj AE 3
28 Nov 2023 22.22 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going. Palakkad Proj AE 3
27 Nov 2023 22.22 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going. Palakkad Proj AE 3
25 Nov 2023 21.52 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going. Palakkad Proj AE 3