Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Jun 2024 | 36.434/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed. Shifting of pipes to Dasannur tank site. | Palakkad Proj AE 3 | |
26 Jun 2024 | 36.434/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed. | Palakkad Proj AE 3 | |
25 Jun 2024 | 36.434/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed. | Palakkad Proj AE 3 | |
24 Jun 2024 | 36.434/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed. | Palakkad Proj AE 3 | |
22 Jun 2024 | 36.434/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
20 Jun 2024 | 36.434/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Project Dn EE | |
07 Jun 2024 | 36.35/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
05 Jun 2024 | 36.22/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
04 Jun 2024 | 36.14/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 | |
03 Jun 2024 | 36.14/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress | Palakkad Proj AE 3 |