Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 Jan 2024 31.13/91.30 km completed. Remaining PVC, HDPE & DI laying progressing, 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress. Palakkad Proj AE 3
27 Jan 2024 30.91/91.30 km completed. Remaining PVC, HDPE & DI laying progressing, 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress. Palakkad Proj AE 3
25 Jan 2024 30.91/91.30 km completed. Remaining PVC, HDPE & DI laying progressing, 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress. Palakkad Proj AE 3
24 Jan 2024 30.77/91.30 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress. Palakkad Proj AE 3
23 Jan 2024 30.57/91.30 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress. Palakkad Proj AE 3
22 Jan 2024 30.57/91.30 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress. Palakkad Proj AE 3
20 Jan 2024 30.36/91.30 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress. Palakkad Proj AE 3
19 Jan 2024 30.30 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress. Palakkad Proj AE 3
18 Jan 2024 30.30 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress. Palakkad Proj AE 3
17 Jan 2024 30.30 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going. Palakkad Proj AE 3