Status Date |
Overall Project Status |
Project Officer |
Contact |
29 Jan 2024 |
31.13/91.30 km completed. Remaining PVC, HDPE & DI laying progressing, 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress.
|
Palakkad Proj AE 3 |
|
27 Jan 2024 |
30.91/91.30 km completed. Remaining PVC, HDPE & DI laying progressing, 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress.
|
Palakkad Proj AE 3 |
|
25 Jan 2024 |
30.91/91.30 km completed. Remaining PVC, HDPE & DI laying progressing, 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress.
|
Palakkad Proj AE 3 |
|
24 Jan 2024 |
30.77/91.30 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress.
|
Palakkad Proj AE 3 |
|
23 Jan 2024 |
30.57/91.30 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress.
|
Palakkad Proj AE 3 |
|
22 Jan 2024 |
30.57/91.30 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress.
|
Palakkad Proj AE 3 |
|
20 Jan 2024 |
30.36/91.30 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress.
|
Palakkad Proj AE 3 |
|
19 Jan 2024 |
30.30 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress.
|
Palakkad Proj AE 3 |
|
18 Jan 2024 |
30.30 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress.
|
Palakkad Proj AE 3 |
|
17 Jan 2024 |
30.30 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going.
|
Palakkad Proj AE 3 |
|