Status Date Overall Project Status Project Officer Contact
06 Nov 2023 19.34 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued. Palakkad Proj AE 3
04 Nov 2023 19.34 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued. Palakkad Proj AE 3
03 Nov 2023 19.34 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued. Palakkad Proj AE 3
02 Nov 2023 19.01 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued. Palakkad Proj AE 3
01 Nov 2023 19.01 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued. Palakkad Proj AE 3
31 Oct 2023 19.01 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued. Palakkad Proj AE 3
30 Oct 2023 19.01 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued. Palakkad Proj AE 3
28 Oct 2023 18.73 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued. Palakkad Proj AE 3
27 Oct 2023 18.73 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued. Palakkad Proj AE 3
26 Oct 2023 18.73 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued. Palakkad Proj AE 3