JJM-2020-21-CWSS to Agali and adjoining Panchayaths-Phase ll -Providing distribution network & amp:FHTC's in Sholayur panchayath

Project JJM-2020-21-CWSS to Agali and adjoining Panchayaths-Phase ll -Providing distribution network & amp:FHTC's in Sholayur panchayath
Project Code PKDJJM052213171
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-2020-21-CWSS to Agali and adjoining Panchayaths-Phase ll -Providing distribution network & amp:FHTC's in Sholayur panchayath
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
AS Amount (Rs) 361981000
AS Number GO(Rt)No.401/2022/WRD
TS Amount (Rs) 304600000
TS Number WRD/KWA-CE(NR)/EST-TS/3982/2022
Total Bill Submitted (Rs) 94894443
Total Bill Paid (Rs) 34059200
Population Benefitted 1000
Capacity in MLD
Actual Project Completion Date 30 May 2024
Coverage JJM-2020-21-CWSS to Agali and adjoining Panchayaths-Phase ll -Providing distribution network & amp:FHTC's in Sholayur panchayath
Work Plan Download

Packages

No. Project Name Location View
1 JJM-2020-21-CWSS to Agali and adjoining Panchayaths-Phase ll -Providing distribution network & amp:FHTC's in Sholayur panchayath Project Division Palakkad

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Jun 2024 36.434/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed. Shifting of pipes to Dasannur tank site. Palakkad Proj AE 3
26 Jun 2024 36.434/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed. Palakkad Proj AE 3
25 Jun 2024 36.434/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed. Palakkad Proj AE 3
24 Jun 2024 36.434/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed. Palakkad Proj AE 3
22 Jun 2024 36.434/91.30 km completed. The remaining PVC, HDPE & DI laying is progressing. 3LL GLSR - Forest survey completed.PWD road (Anaikatti - Sholayur Road, Karayur - Vannanthara Road) work progress Palakkad Proj AE 3

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/06/2023
Scheduled date of Completion of the Project 25 Jun 2024
Expected date of Completion 25/04/2024

Processing Dates

AS Date 13 May 2022
TS Date 21 Oct 2022