Status Date |
Overall Project Status |
Project Officer |
Contact |
24 Nov 2023 |
21.52 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going. |
Palakkad Proj AE 3 |
|
23 Nov 2023 |
21.52km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going |
Palakkad Proj AE 3 |
|
22 Nov 2023 |
21.52km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going. |
Palakkad Proj AE 3 |
|
21 Nov 2023 |
20.83 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going. |
Palakkad Proj AE 3 |
|
20 Nov 2023 |
20.43 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going.
|
Palakkad Proj AE 3 |
|
18 Nov 2023 |
20.31 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going.
|
Palakkad Proj AE 3 |
|
17 Nov 2023 |
20.31 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going.
|
Palakkad Proj AE 3 |
|
16 Nov 2023 |
20.31 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going.
|
Palakkad Proj AE 3 |
|
15 Nov 2023 |
20.31 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going.
|
Palakkad Proj AE 3 |
|
14 Nov 2023 |
20.31 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going.
|
Palakkad Proj AE 3 |
|