Status Date |
Overall Project Status |
Project Officer |
Contact |
20 Dec 2023 |
27.25 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going.
|
Palakkad Proj AE 3 |
|
19 Dec 2023 |
27.25 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going.
|
Palakkad Proj AE 3 |
|
16 Dec 2023 |
26.52 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going.
|
Palakkad Proj AE 3 |
|
15 Dec 2023 |
26.52 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going.
|
Palakkad Proj AE 3 |
|
14 Dec 2023 |
26.23 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going.
|
Palakkad Proj AE 3 |
|
13 Dec 2023 |
26.23 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going.
|
Palakkad Proj AE 3 |
|
12 Dec 2023 |
25.36 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going.
|
Palakkad Proj AE 3 |
|
11 Dec 2023 |
25.36 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going.
|
Palakkad Proj AE 3 |
|
08 Dec 2023 |
25.36 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going.
|
Palakkad Proj AE 3 |
|
07 Dec 2023 |
23.66 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) issued, road restoration on going.
|
Palakkad Proj AE 3 |
|