Status Date Overall Project Status Project Officer Contact
09 Oct 2023 14.84 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued. Palakkad Proj AE 3
07 Oct 2023 14.46 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued. Palakkad Proj AE 3
06 Oct 2023 14.46 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued. Palakkad Proj AE 3
05 Oct 2023 13.31 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued. Palakkad Proj AE 3
04 Oct 2023 13.31 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued. Palakkad Proj AE 3
03 Oct 2023 13.31 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued. Palakkad Proj AE 3
30 Sep 2023 12.21 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued. Palakkad Proj AE 3
29 Sep 2023 12.21 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued. Palakkad Proj AE 3
27 Sep 2023 12.21 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued. Palakkad Proj AE 3
26 Sep 2023 11.62 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued. Palakkad Proj AE 3