Status Date |
Overall Project Status |
Project Officer |
Contact |
09 Oct 2023 |
14.84 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued.
|
Palakkad Proj AE 3 |
|
07 Oct 2023 |
14.46 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued.
|
Palakkad Proj AE 3 |
|
06 Oct 2023 |
14.46 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued.
|
Palakkad Proj AE 3 |
|
05 Oct 2023 |
13.31 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued.
|
Palakkad Proj AE 3 |
|
04 Oct 2023 |
13.31 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued. |
Palakkad Proj AE 3 |
|
03 Oct 2023 |
13.31 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued. |
Palakkad Proj AE 3 |
|
30 Sep 2023 |
12.21 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued.
|
Palakkad Proj AE 3 |
|
29 Sep 2023 |
12.21 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued. |
Palakkad Proj AE 3 |
|
27 Sep 2023 |
12.21 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued. |
Palakkad Proj AE 3 |
|
26 Sep 2023 |
11.62 km completed. Remaining 90 mm, 160 mm & 110 mm PVC laying progressing, Road formation work on going, Forest survey completed.PWD road cutting permission (Karayur - Vannamthara Road,Anakatty - Marappalam Road,kottathara chandakada bridge to anakatti ) not issued.
|
Palakkad Proj AE 3 |
|