Status Date Overall Project Status Project Officer Contact
16 Jan 2024 30.30 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going. Palakkad Proj AE 3
12 Jan 2024 30.13 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going. Palakkad Proj AE 3
11 Jan 2024 29.50 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going. Palakkad Proj AE 3
10 Jan 2024 29.38 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going. Palakkad Proj AE 3
09 Jan 2024 29.38 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going. Palakkad Proj AE 3
08 Jan 2024 29.38 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going. Palakkad Proj AE 3
08 Jan 2024 29.38 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going. Palakkad Proj AE 3
06 Jan 2024 29.38 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going. Palakkad Proj AE 3
05 Jan 2024 29.38 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going. Palakkad Proj AE 3
04 Jan 2024 27.81 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going. Palakkad Proj AE 3