Status Date |
Overall Project Status |
Project Officer |
Contact |
03 Jan 2024 |
27.81 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going.
|
Palakkad Proj AE 3 |
|
01 Jan 2024 |
27.81 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going.
|
Palakkad Proj AE 3 |
|
30 Dec 2023 |
27.81 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going.
|
Palakkad Proj AE 3 |
|
29 Dec 2023 |
27.81 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going.
|
Palakkad Proj AE 3 |
|
28 Dec 2023 |
27.81 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going.
|
Palakkad Proj AE 3 |
|
27 Dec 2023 |
27.81 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going.
|
Palakkad Proj AE 3 |
|
26 Dec 2023 |
27.81 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going.
|
Palakkad Proj AE 3 |
|
23 Dec 2023 |
27.81 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going.
|
Palakkad Proj AE 3 |
|
22 Dec 2023 |
27.81 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going.
|
Palakkad Proj AE 3 |
|
21 Dec 2023 |
27.81 km completed. Remaining 90 mm, 160 mm, 140 mm & 110 mm PVC laying progressing, 3LL OHSR - Road formation work on going, Forest survey completed.PWD road (Anaikatti - Sholayur Road ,Karayur - Vannanthara Road) work progress,road restoration on going.
|
Palakkad Proj AE 3 |
|