| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 31 Jan 2025 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 28 Jan 2025 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 25 Jan 2025 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 22 Jan 2025 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 19 Jan 2025 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 16 Jan 2025 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 13 Jan 2025 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 10 Jan 2025 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 07 Jan 2025 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 04 Jan 2025 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 |