Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
06 Nov 2024 | Pipe laid 2700 m out of 2700 m and FHTC 850 Nos out of 2500 Nos completed. Road restoration work completed. | Kannur WS Sn AE 2 | |
03 Nov 2024 | Pipe laid 2700 m out of 2700 m and FHTC 800 Nos out of 2500 Nos completed. Road restoration work completed. | Kannur WS Sn AE 2 | |
31 Oct 2024 | Pipe laid 2700 m out of 2700 m and FHTC 800 Nos out of 2500 Nos completed. Road restoration work completed. | Kannur WS Sn AE 2 | |
31 Oct 2024 | Pipe laid 2700 m out of 2700 m and FHTC 750 Nos out of 2500 Nos completed. Road restoration work completed. | Kannur WS Sn AE 2 | |
28 Oct 2024 | Pipe laid 2700 m out of 2700 m and FHTC 750 Nos out of 2500 Nos completed. Road restoration work completed. | Kannur WS Sn AE 2 | |
22 Oct 2024 | Pipe laid 2700 m out of 2700 m and FHTC 750 Nos out of 2500 Nos completed. Road restoration work completed. | Kannur WS Sn AE 2 | |
20 Oct 2024 | Pipe laid 2700 m out of 2700 m and FHTC 650 Nos out of 2500 Nos completed. Road restoration work is progressing | Kannur WS Sn AE 2 | |
17 Oct 2024 | Pipe laid 2700 m out of 2700 m and FHTC 650 Nos out of 2500 Nos completed. Road restoration work is progressing | Kannur WS Sn AE 2 | |
14 Oct 2024 | Pipe laid 2700 m out of 2700 m and FHTC 650 Nos out of 2500 Nos completed. Road restoration work is progressing | Kannur WS Sn AE 2 | |
11 Oct 2024 | Pipe laid 2700 m out of 2700 m and FHTC 650 Nos out of 2500 Nos completed. Road restoration work is progressing. | Kannur WS Sn AE 2 |