| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Jan 2025 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 29 Dec 2024 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 26 Dec 2024 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 23 Dec 2024 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 29 Dec 2024 | Pipe laid 2300 m out of 2300 m and FHTC 1100 Nos out of 2150 Nos completed,, Road restoration work in progres | Kannur WS Sn AE 2 | |
| 26 Dec 2024 | Pipe laid 2300 m out of 2300 m and FHTC 1100 Nos out of 2150 Nos completed,, Road restoration work in progres | Kannur WS Sn AE 2 | |
| 23 Dec 2024 | Pipe laid 2300 m out of 2300 m and FHTC 1100 Nos out of 2150 Nos completed,, Road restoration work in progres | Kannur WS Sn AE 2 | |
| 20 Dec 2024 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 17 Dec 2024 | Pipe laid 2700 m out of 2700 m and FHTC 850 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 14 Dec 2024 | Pipe laid 2700 m out of 2700 m and FHTC 850 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 |