Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
08 Sep 2024 | Pipe laid 2700 m out of 2700 m and FHTC 530 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
04 Sep 2024 | Pipe laid 2700 m out of 2700 m and FHTC 510 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
01 Sep 2024 | Pipe laid 2700 m out of 2700 m and FHTC 510 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
29 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 510 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
25 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 510 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
22 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 500 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
19 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 500 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
16 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 500 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
13 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 500 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
10 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 500 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 |