Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Dec 2024 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
23 Dec 2024 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
29 Dec 2024 | Pipe laid 2300 m out of 2300 m and FHTC 1100 Nos out of 2150 Nos completed,, Road restoration work in progres | Kannur WS Sn AE 2 | |
26 Dec 2024 | Pipe laid 2300 m out of 2300 m and FHTC 1100 Nos out of 2150 Nos completed,, Road restoration work in progres | Kannur WS Sn AE 2 | |
23 Dec 2024 | Pipe laid 2300 m out of 2300 m and FHTC 1100 Nos out of 2150 Nos completed,, Road restoration work in progres | Kannur WS Sn AE 2 | |
20 Dec 2024 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
17 Dec 2024 | Pipe laid 2700 m out of 2700 m and FHTC 850 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
14 Dec 2024 | Pipe laid 2700 m out of 2700 m and FHTC 850 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
11 Dec 2024 | Pipe laid 2700 m out of 2700 m and FHTC 850 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
08 Dec 2024 | Pipe laid 2700 m out of 2700 m and FHTC 850 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 |