| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 14 Oct 2024 | Pipe laid 2700 m out of 2700 m and FHTC 650 Nos out of 2500 Nos completed. Road restoration work is progressing | Kannur WS Sn AE 2 | |
| 11 Oct 2024 | Pipe laid 2700 m out of 2700 m and FHTC 650 Nos out of 2500 Nos completed. Road restoration work is progressing. | Kannur WS Sn AE 2 | |
| 08 Oct 2024 | Pipe laid 2700 m out of 2700 m and FHTC 650 Nos out of 2500 Nos completed. Road restoration work is progressing. | Kannur WS Sn AE 2 | |
| 05 Oct 2024 | Pipe laid 2700 m out of 2700 m and FHTC 650 Nos out of 2500 Nos completed. Road restoration work is progressing. | Kannur WS Sn AE 2 | |
| 02 Oct 2024 | Pipe laid 2700 m out of 2700 m and FHTC 650 Nos out of 2500 Nos completed. Road restoration work is progressing. | Kannur WS Sn AE 2 | |
| 29 Sep 2024 | Pipe laid 2700 m out of 2700 m and FHTC 650 Nos out of 2500 Nos completed. Road restoration work is progressing. | Kannur WS Sn AE 2 | |
| 26 Sep 2024 | Pipe laid 2700 m out of 2700 m and FHTC 630 Nos out of 2500 Nos completed. Road restoration work is progressing. | Kannur WS Sn AE 2 | |
| 23 Sep 2024 | Pipe laid 2700 m out of 2700 m and FHTC 600 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
| 20 Sep 2024 | Pipe laid 2700 m out of 2700 m and FHTC 600 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
| 17 Sep 2024 | Pipe laid 2700 m out of 2700 m and FHTC 570 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 |