08 Jul 2024 Pipe laid 2700 m out of 2700 m and FHTC380 Nos out of 2500 Nos completed. Kannur WS Sn AE 2
05 Jul 2024 Pipe laid 2700 m out of 2700 m and FHTC380 Nos out of 2500 Nos completed. Kannur WS Sn AE 2
02 Jul 2024 Pipe laid 2700 m out of 2700 m and FHTC380 Nos out of 2500 Nos completed. Kannur WS Sn AE 2
29 Jun 2024 Pipe laid 2700 m out of 2700 m and FHTC380 Nos out of 2500 Nos completed. Kannur WS Sn AE 2
26 Jun 2024 Pipe laid 2700 m out of 2700 m and FHTC380 Nos out of 2500 Nos completed. Kannur WS Sn AE 2
23 Jun 2024 Pipe laid 2700 m out of 2700 m and FHTC380 Nos out of 2500 Nos completed. Kannur WS Sn AE 2
20 Jun 2024 Pipe laid 2700 m out of 2700 m and FHTC 260 Nos out of 2500 Nos completed. Kannur WS Sn AE 2
17 Jun 2024 Pipe laid 2700 m out of 2700 m and FHTC 200Nos out of 2500 Nos completed. Kannur WS Sn AE 2
14 Jun 2024 Pipe laid 2700 m out of 2700 m and FHTC 200Nos out of 2500 Nos completed. Kannur WS Sn AE 2
11 Jun 2024 Pipe laid 2700 m out of 2700 m and FHTC 200Nos out of 2500 Nos completed. Kannur WS Sn AE 2