Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Feb 2025 | Pipe laid 2700 m out of 2700 m and FHTC 950 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
21 Feb 2025 | Pipe laid 2700 m out of 2700 m and FHTC 950 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
18 Feb 2025 | Pipe laid 2700 m out of 2700 m and FHTC 950 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
15 Feb 2025 | Pipe laid 2700 m out of 2700 m and FHTC 950 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
12 Feb 2025 | Pipe laid 2700 m out of 2700 m and FHTC 950 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
09 Feb 2025 | Pipe laid 2700 m out of 2700 m and FHTC 950 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
06 Feb 2025 | Pipe laid 2700 m out of 2700 m and FHTC 950 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
03 Feb 2025 | Pipe laid 2700 m out of 2700 m and FHTC 950 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
31 Jan 2025 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
28 Jan 2025 | Pipe laid 2700 m out of 2700 m and FHTC 880 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 |