| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 14 Sep 2024 | Pipe laid 2700 m out of 2700 m and FHTC 560 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
| 11 Sep 2024 | Pipe laid 2700 m out of 2700 m and FHTC 550 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
| 08 Sep 2024 | Pipe laid 2700 m out of 2700 m and FHTC 530 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
| 04 Sep 2024 | Pipe laid 2700 m out of 2700 m and FHTC 510 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
| 01 Sep 2024 | Pipe laid 2700 m out of 2700 m and FHTC 510 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
| 29 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 510 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
| 25 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 510 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
| 22 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 500 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
| 19 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 500 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
| 16 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 500 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 |