Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Jun 2024 Pipe laid 2700 m out of 2700 m and FHTC 200Nos out of 2500 Nos completed. Kannur WS Sn AE 2
05 Jun 2024 Pipe laid 2700 m out of 2700 m and FHTC 195Nos out of 2500 Nos completed. Kannur WS Sn AE 2
02 Jun 2024 Pipe laid 1500 m out of 2700 m and FHTC 172Nos out of 2500 Nos completed. Kannur WS Sn AE 2
30 May 2024 Pipe laid 1500 m out of 2700 m and FHTC 172Nos out of 2500 Nos completed. Kannur WS Sn AE 2
27 May 2024 Pipe laid 1500 m out of 2700 m and FHTC 170 Nos out of 2500 Nos completed. Kannur WS Sn AE 2
24 May 2024 Pipe laid 1500 m out of 2700 m and FHTC 160 Nos out of 2500 Nos completed. Kannur WS Sn AE 2
21 May 2024 Pipe laid 1500 m out of 2700 m and FHTC 160 Nos out of 2500 Nos completed. Kannur WS Sn AE 2
18 May 2024 Pipe laid 1200 m out of 2700 m and FHTC 145 Nos out of 2500 Nos completed. Kannur WS Sn AE 2
15 May 2024 Pipe laid 1000 m out of 2700 m and FHTC 140 Nos out of 2500 Nos completed. Kannur WS Sn AE 2
12 May 2024 Pipe laid 738 m out of 2700 m and FHTC 120 Nos out of 2500 Nos completed. Kannur WS Sn AE 2