Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
08 Jun 2024 | Pipe laid 2700 m out of 2700 m and FHTC 200Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
05 Jun 2024 | Pipe laid 2700 m out of 2700 m and FHTC 195Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
02 Jun 2024 | Pipe laid 1500 m out of 2700 m and FHTC 172Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
30 May 2024 | Pipe laid 1500 m out of 2700 m and FHTC 172Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
27 May 2024 | Pipe laid 1500 m out of 2700 m and FHTC 170 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
24 May 2024 | Pipe laid 1500 m out of 2700 m and FHTC 160 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
21 May 2024 | Pipe laid 1500 m out of 2700 m and FHTC 160 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
18 May 2024 | Pipe laid 1200 m out of 2700 m and FHTC 145 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
15 May 2024 | Pipe laid 1000 m out of 2700 m and FHTC 140 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
12 May 2024 | Pipe laid 738 m out of 2700 m and FHTC 120 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 |