| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 03 Mar 2025 | Pipe laid 2700 m out of 2700 m and FHTC 950 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 27 Feb 2025 | Pipe laid 2700 m out of 2700 m and FHTC 950 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 24 Feb 2025 | Pipe laid 2700 m out of 2700 m and FHTC 950 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 21 Feb 2025 | Pipe laid 2700 m out of 2700 m and FHTC 950 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 18 Feb 2025 | Pipe laid 2700 m out of 2700 m and FHTC 950 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 15 Feb 2025 | Pipe laid 2700 m out of 2700 m and FHTC 950 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 12 Feb 2025 | Pipe laid 2700 m out of 2700 m and FHTC 950 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 09 Feb 2025 | Pipe laid 2700 m out of 2700 m and FHTC 950 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 06 Feb 2025 | Pipe laid 2700 m out of 2700 m and FHTC 950 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 | |
| 03 Feb 2025 | Pipe laid 2700 m out of 2700 m and FHTC 950 Nos out of 2500 Nos completed. Road restoration work completed | Kannur WS Sn AE 2 |