Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Jul 2025 Pipe laid 2700 m out of 2700 m and FHTC 978Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing,3 rd & part bill submitted Kannur WS Sn AE 2
30 Jun 2025 Pipe laid 2700 m out of 2700 m and FHTC 978Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing,3 rd & part bill submitted Kannur WS Sn AE 2
27 Jun 2025 Pipe laid 2700 m out of 2700 m and FHTC 978Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing,3 rd & part bill submitted Kannur WS Sn AE 2
24 Jun 2025 Pipe laid 2700 m out of 2700 m and FHTC 978Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing,3 rd & part bill submitted Kannur WS Sn AE 2
20 Jun 2025 Pipe laid 2700 m out of 2700 m and FHTC 978Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing,3 rd & part bill submitted Kannur WS Sn AE 2
16 Jun 2025 Pipe laid 2700 m out of 2700 m and FHTC 968Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing,3 rd & part bill submitted Kannur WS Sn AE 2
11 Jun 2025 Pipe laid 2700 m out of 2700 m and FHTC 968Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing,3 rd & part bill submitted Kannur WS Sn AE 2
05 Jun 2025 Pipe laid 2700 m out of 2700 m and FHTC 968Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing,3 rd & part bill submitted Kannur WS Sn AE 2
31 May 2025 Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing,3 rd & part bill submitted Kannur WS Sn AE 2
27 May 2025 Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing,3 rd & part bill submitted Kannur WS Sn AE 2