Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
07 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 500 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
04 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 485 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
01 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 485 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
29 Jul 2024 | Pipe laid 2700 m out of 2700 m and FHTC 480 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
26 Jul 2024 | Pipe laid 2700 m out of 2700 m and FHTC 480 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
23 Jul 2024 | Pipe laid 2700 m out of 2700 m and FHTC 480 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
20 Jul 2024 | Pipe laid 2700 m out of 2700 m and FHTC 480 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
17 Jul 2024 | Pipe laid 2700 m out of 2700 m and FHTC 480 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
14 Jul 2024 | Pipe laid 2700 m out of 2700 m and FHTC 480 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
11 Jul 2024 | Pipe laid 2700 m out of 2700 m and FHTC380 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 |