| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 Apr 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing | Kannur WS Sn AE 2 | |
| 27 Apr 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing | Kannur WS Sn AE 2 | |
| 24 Apr 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing | Kannur WS Sn AE 2 | |
| 21 Apr 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing | Kannur WS Sn AE 2 | |
| 18 Apr 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing | Kannur WS Sn AE 2 | |
| 15 Apr 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing | Kannur WS Sn AE 2 | |
| 12 Apr 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing | Kannur WS Sn AE 2 | |
| 09 Apr 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing | Kannur WS Sn AE 2 | |
| 06 Apr 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing | Kannur WS Sn AE 2 | |
| 03 Apr 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing | Kannur WS Sn AE 2 |