| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 13 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 500 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
| 10 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 500 Nos out of 2500 Nos completed | Kannur WS Sn AE 2 | |
| 07 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 500 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
| 04 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 485 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
| 01 Aug 2024 | Pipe laid 2700 m out of 2700 m and FHTC 485 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
| 29 Jul 2024 | Pipe laid 2700 m out of 2700 m and FHTC 480 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
| 26 Jul 2024 | Pipe laid 2700 m out of 2700 m and FHTC 480 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
| 23 Jul 2024 | Pipe laid 2700 m out of 2700 m and FHTC 480 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
| 20 Jul 2024 | Pipe laid 2700 m out of 2700 m and FHTC 480 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
| 17 Jul 2024 | Pipe laid 2700 m out of 2700 m and FHTC 480 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 |