Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Jan 2024 | 40200m pipe laid . 510 HTC given | Koothuparamba Proj AE 2 | |
09 Jan 2024 | 38400m pipe laid . 480 HTC given | Koothuparamba Proj AE 2 | |
01 Jan 2024 | 40000m pipe laid . 600HTC given | Koothuparamba Proj AE 2 | |
08 Dec 2023 | 36500m pipe laid . 420 HTC given | Koothuparamba Proj AE 2 | |
04 Dec 2023 | 35000m pipe laid . 390 HTC given | Koothuparamba Proj AE 2 | |
30 Nov 2023 | 35000m pipe laid . 372 HTC given | Koothuparamba Proj AE 2 | |
17 Nov 2023 | 34200m pipe laid . 330 HTC given | Koothuparamba Proj AE 2 | |
13 Nov 2023 | 30000m pipe laid . 308 HTC given | Koothuparamba Proj AE 2 | |
08 Nov 2023 | 29000m pipe laid . 280 HTC given | Koothuparamba Proj AE 2 | |