| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 07 Mar 2024 | 65300m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
| 04 Mar 2024 | 62100m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
| 29 Feb 2024 | 60200m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
| 27 Feb 2024 | 58000m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
| 24 Feb 2024 | 57200m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
| 22 Feb 2024 | 56500m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
| 19 Feb 2024 | 51800m pipe laid . 990 HTC given | Koothuparamba Proj AE 2 | |
| 18 Feb 2024 | 51200m pipe laid . 990 HTC given | Koothuparamba Proj AE 2 | |
| 17 Feb 2024 | 50580m pipe laid . 990 HTC given | Koothuparamba Proj AE 2 | |