Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
25 May 2024 | 105102m pipe laid 995 htc | Koothuparamba Proj AE 2 | |
21 May 2024 | 100235m pipe laid 995 htc | Koothuparamba Proj AE 2 | |
21 May 2024 | 10235m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
16 May 2024 | 99321m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
13 May 2024 | 95665m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
09 May 2024 | 90350m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
06 May 2024 | 89920m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
02 May 2024 | 88514m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
30 Apr 2024 | 82125m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
25 Apr 2024 | 80710 m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 |