| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 13 Aug 2024 | 121000 m pipe laid 995 HTC | Koothuparamba Proj AE 2 | |
| 09 Aug 2024 | 121000 m pipe laid 995 HTC | Koothuparamba Proj AE 2 | |
| 07 Aug 2024 | 121000 m pipe laid 995 HTC | Koothuparamba Proj AE 2 | |
| 02 Aug 2024 | 121000 m pipe laid 995 HTC | Koothuparamba Proj AE 2 | |
| 27 Jul 2024 | 121000 m pipe laid 995 HTC | Koothuparamba Proj AE 2 | |
| 17 Jul 2024 | 119800m pipe laid 995 HTC | Koothuparamba Proj AE 2 | |
| 08 Jul 2024 | 119000m pipe laid 995 HTC | Koothuparamba Proj AE 2 | |
| 03 Jul 2024 | 118000m pipe laid 995 HTC | Koothuparamba Proj AE 2 | |
| 27 Jun 2024 | 117315m pipe laid 995 HTC | Koothuparamba Proj AE 2 | |