Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
22 Apr 2024 | 78590 m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
18 Apr 2024 | 75985m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
15 Apr 2024 | 75715m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
11 Apr 2024 | 75620m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
09 Apr 2024 | 75580m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
05 Apr 2024 | 75420m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
02 Apr 2024 | 75000m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
02 Apr 2024 | 75000 | Koothuparamba Proj AE 2 | |
28 Mar 2024 | 73800m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
25 Mar 2024 | 73050m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 |