| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 06 Jan 2026 | 143700 m pipe laid 327 HTC and 1641FHTC given | Koothuparamba Proj AE 2 | |
| 31 Dec 2025 | 143700 m pipe laid 320 HTC and 1640 FHTC given | Koothuparamba Proj AE 2 | |
| 26 Dec 2025 | 143700 m pipe laid 320 HTC and 1640 FHTC given | Koothuparamba Proj AE 2 | |
| 22 Dec 2025 | 143700 m pipe laid 320 HTC and 1640 FHTC given | Koothuparamba Proj AE 2 | |
| 17 Dec 2025 | 143700 m pipe laid 320 HTC and 1640 FHTC given | Koothuparamba Proj AE 2 | |
| 09 Dec 2025 | 143700 m pipe laid 302 HTC and 1619 FHTC given | Koothuparamba Proj AE 2 | |
| 06 Dec 2025 | 143700 m pipe laid 302 HTC and 1619 FHTC given | Koothuparamba Proj AE 2 | |
| 01 Dec 2025 | 143700 m pipe laid 312 HTC and 1555 FHTC given | Koothuparamba Proj AE 2 | |
| 26 Nov 2025 | 143700 m pipe laid 312 HTC and 1555 FHTC given | Koothuparamba Proj AE 2 | |