JJM-Kannur District-WSS to Kottiyur,Kelakam and Kanichar Panchayaths-Laying Distribution system from WTP and Providing FHTCs -ZoneIV &V
Project |
JJM-Kannur District-WSS to Kottiyur,Kelakam and Kanichar Panchayaths-Laying Distribution system from WTP and Providing FHTCs -ZoneIV &V |
Project Code |
KNRJJM092214220 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-01 |
Description |
Laying Distribution line and providing 2899 FHTC .total distribution line proposed in this project is 105734m for main line and for laying rider line and parallel line is 12032 for avoiding road crossing .Additional length of 29190 m pipes included for FHTCs |
Status |
On-going |
District |
Kannur |
Executing Office |
Koothuparamba Project Sn No2 |
AS Amount (Rs) |
1284997000
|
AS Number |
G.O(Rt) No 489/2021/WRD |
TS Amount (Rs) |
289600000 |
TS Number |
WRD/KWA-CE(NR)/EST_TS/3689/2022_26_2_1 |
Total Bill Submitted (Rs) |
175208402 |
Total Bill Paid (Rs) |
95952095 |
Population Benefitted |
11596 |
Capacity in MLD |
11.00 |
Actual Project Completion Date |
22 Jan 2024 |
Coverage |
100% |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM-Kannur District-WSS to Kottiyur,Kelakam and Kanichar Panchayaths-Laying Distribution system from WTP and Providing FHTCs -ZoneIV &V |
Koothuparamba Project Sn No2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
04 Jul 2025 |
136354.13 m pipe laid 425 HTC and 1048 FHTC given. |
Koothuparamba Proj AE 2 |
|
01 Jul 2025 |
136354.13 m pipe laid 425 HTC and 1048 FHTC given. |
Koothuparamba Proj AE 2 |
|
27 Jun 2025 |
136354.13 m pipe laid 455 HTC and 1018 FHTC given. |
Koothuparamba Proj AE 2 |
|
23 Jun 2025 |
136354.13 m pipe laid 455 HTC and 1018 FHTC given. |
Koothuparamba Proj AE 2 |
|
19 Jun 2025 |
136354.13 m pipe laid 455 HTC and 1018 FHTC given. |
Koothuparamba Proj AE 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
16/02/2023 |
Scheduled date of Completion of the Project |
22 Jan 2024 |
Expected date of Completion |
30/09/2025 |
Processing Dates
AS Date |
18 Sep 2022 |
TS Date |
25 Nov 2022 |