| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 19 Jun 2024 | 116200m pipe laid 995 HTC | Koothuparamba Proj AE 2 | |
| 13 Jun 2024 | 114600m pipe laid 995 HTC | Koothuparamba Proj AE 2 | |
| 07 Jun 2024 | 114586m pipe laid 995 HTC | Koothuparamba Proj AE 2 | |
| 06 Jun 2024 | 114586m pipe laid 995 HTC | Koothuparamba Proj AE 2 | |
| 03 Jun 2024 | 110320m pipe laid 995 HTC | Koothuparamba Proj AE 2 | |
| 29 May 2024 | 108220m pipe laid 995 htc | Koothuparamba Proj AE 2 | |
| 25 May 2024 | 105102m pipe laid 995 htc | Koothuparamba Proj AE 2 | |
| 21 May 2024 | 100235m pipe laid 995 htc | Koothuparamba Proj AE 2 | |
| 21 May 2024 | 10235m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 | |
| 16 May 2024 | 99321m pipe laid . 995 HTC given | Koothuparamba Proj AE 2 |