Status Date Overall Project Status Project Officer Contact
21 Mar 2024 72700m pipe laid . 995 HTC given Koothuparamba Proj AE 2
19 Mar 2024 71500m pipe laid . 995 HTC given Koothuparamba Proj AE 2
14 Mar 2024 69300m pipe laid . 995 HTC given Koothuparamba Proj AE 2
11 Mar 2024 67800m pipe laid . 995 HTC given Koothuparamba Proj AE 2
07 Mar 2024 65300m pipe laid . 995 HTC given Koothuparamba Proj AE 2
04 Mar 2024 62100m pipe laid . 995 HTC given Koothuparamba Proj AE 2
29 Feb 2024 60200m pipe laid . 995 HTC given Koothuparamba Proj AE 2
27 Feb 2024 58000m pipe laid . 995 HTC given Koothuparamba Proj AE 2
24 Feb 2024 57200m pipe laid . 995 HTC given Koothuparamba Proj AE 2
22 Feb 2024 56500m pipe laid . 995 HTC given Koothuparamba Proj AE 2